CongratulationsÌýto our colleagues at Teesside Beam Mill who have resumed production following a zero-harm summer maintenance programme.
The annual 16-day campaign saw the team, supported by more than 180 contractors, successfully undertake a huge volume of planned maintenance and improvements.
The largest project involved repairs to the refractory wall of the mill’s re-heat furnace – a task which saw teams work in a 24-hour rotation.
As the UK’s only manufacturer of large constructional steel sections, it was vital this planned programme of works was completed safely and on time. And that’s exactly what the team did.
Huge thanks to our colleagues and contractors for your outstanding efforts – together you have ensured we can continue to deliver the products our customers require in a timely manner.